FLATNaturalReal stone paintBrief construction plan
FLATReal stone paintIntroduction:
FLATReal stone paintIt is a unique environmentally friendly material for interior and exterior building walls. It is made from pure acrylic emulsion, natural stone powder and various imported additives through a special process. After spraying, it ensures that all substrates are covered with a layer that achieves a surface effect almost indistinguishable from granite slabs.
Functions: easy to construct, strong texture, appearance closely resembling granite, good toughness, crack resistance, high strength, impact resistance, no fading, no aging, flame retardant, heat resistant, good weather resistance, guaranteed for more than fifteen years; good texture, easy to shape, strong expressiveness, high hardness, no discoloration, dirt resistance, good cleanability, water resistance, crack resistance and seepage resistance.
FLATReal stone paintConstruction steps:
1. Substrate treatment
2. Apply alkali-resistant sealing primer
3. Pointing
4. Spray-applied real stone paint
5. Paint surface flattening
6. Remove the adhesive tape
7. Sand the wall surface
8. Spray an organic silicone topcoat.
First: Substrate
1. Substrate requirements
⑴Newly built walls require adequate curing and drying; for old walls that have become damp and peeled, the base plastering shall be redone.
⑵The substrate shall be flat and clean, free of oil stains, loose dust or other contaminants.
⑶For old coatings on old walls or other substrates, their adhesion shall be confirmed by testing; if the adhesion is poor, then
Stripping.
(4) Confirm whether the substrate strength, flatness, acidity/alkalinity and moisture content meet the specified standards.
2. Methods and standards for accepting the substrate:
1) Wall flatness and verticality: use a 2M long spirit level against the wall; the unevenness must not exceed ±2mm;
2) Squareness of internal and external corners: check with a square ruler; the error must not exceed ±2mm
3) Moisture content of the substrate: below 10% moisture content and below 10 pH. On sunny days, lay transparent adhesive tape flat on the substrate, using the tape
4) Seal the four sides with adhesive tape. After 2-4 hours, if condensation appears inside the tape, the moisture content of the substrate is high and it is not suitable for construction.
5) By visual inspection or instrument testing, confirm whether the substrate strength, flatness, acidity/alkalinity, and moisture content meet the specified standards.
3. Common problems with the substrate and their treatment methods
1) Treatment method for uneven walls: for uneven walls, first roughly level with a coarser leveling putty, then use a finer
Apply putty flat to ensure an attractive wall surface and facilitate coating application.
2) Treatment method for non-vertical internal and external corners: for internal and external corners that are not straight or not flat, first level them in large areas with a coarser leveling putty; in severe cases,
must first be repaired with a mixture of cement and sand, and then leveled with a large putty knife. Achieve vertical and parallel internal and external corners
3) Treatment of seams and repair marks on the wall surface: repair with a mixture of cement and sand, then level extensively with putty.
4) Treatment for high moisture content: if the wall moisture content is higher than 10% and the pH is higher than 10, the curing period should be extended.
4. Precautions
II. Construction process for primer
Method:1 Roller coating method, 2 Spray coating method,
1 Roller coating method A. Construction tool — roller
B. Preparation before roller coating:
1) Remove foreign matter from the substrate
2) The water-based primer can be added at approximately 10% by volume.Left and rightDilute with clean water and stir evenly
C. Procedures and requirements,
Use a wool roller.tubeApply the water-based primer evenly in two coats using the cross-rolling method.
Thickness:30 microns 0.15KG/㎡
2. Spraying method,
A. Construction tools: primer spray gun, air compressor
B, Preparation before spraying:
1) Remove foreign matter from the substrate. 2) The water-based primer can be applied without adding water; if dilution is needed, add about 10% clean water by volume and stir evenly
C. Procedures and requirements,
1) Start the air compressor and adjust the pressure to 8KG,
2) Load the water-based primer into the spray gun and connect it to the air compressor.
3) Apply two coats evenly by cross-roller coating.
4) Thickness: 30 microns, 0.15KG/㎡
3. Common problems and their treatment methods
1) Uneven coating: areas with uneven coating must be repaired,
2) If traces remain on the substrate after applying the primer at joints: the substrate should be repaired before applying the primer.
4. Precautions:
1) During primer construction, the wall temperature shall not be lower than 10℃, the wall moisture content shall be less than 10%, and the air humidity shall be less than50%
2) Application should be as uniform as possible.
2) Those that do not meet the technical requirements shall be repaired.
3) Construction cannot be carried out when the temperature is below 5.
III. Making the Shape (Jointing):
1. Tools and materials: masking tape, chalk line, straightedge, color pen
2. Production process and requirements:
1) Before jointing, the construction pattern should be designed properly,
2) According to the designed joint size, select the width of the masking tape. 3) Snap the grid joint lines on the wall according to the designed pattern,
4) Mask the area within the dividing lines with paper tape. Pull a through line on the same wall and snap it straight.
3. Points for attention,
1) If no jointing is required, this process is not needed.
2) The joint size should be coordinated, and the lines should be vertical.
4. Common problems and solutions
IV.Real stonePaintconstruction:
A. Construction tools: air compressor,Real stonePaint-specific spray gun, putty knife
B, Preparation before spraying:
1) Check whether the primer spraying and jointing meet the requirements.
2) Store for a period of timeReal stonePour the paint into the mixing bucket and mix evenly with a mixer. If dilution with water is required, add
Standard method (generally no dilution), place inStir evenly with about 5% water.
3) Protect facilities around the area to be sprayed (doors, windows, guardrails, etc.) with old newspapers or tape to prevent spraying
damage during.
C. Procedures and requirements:
1) One method is spray application:
A. That is, use a dedicated spray gun for application; the air compressor pressure must reach 8KG or above.
B. Keep the spray gun nozzle perpendicular to the spraying surface, with a spraying distance of about 30-40cm, and keep the spray gun moving at a certain
Speed, spray using the cross spraying method.
C. Completed in one pass during spraying D. After completionReal stoneTotal paint thickness~3mm is appropriate; the floating points are required to be uniform and the color consistent,
D. Notes:
1) Construction cannot be carried out when the temperature is below 5°C or the wind is above force 4
2) Spray the rock flake paint only 12 hours after the primer is sprayed.
3) SelectReal stonePaint-specific spray gun, with air pressure controlled at8 kg/cm²,
4) Wall temperature above 10 degrees Celsius, air humidity less than 80%,
5), thickness approximately 2-3mm. To ensure uniform color, it is recommended to use a thin-spray, multi-layer method, with an interval of 2 hours between layers, dry
DryCan be sanded only after 24 hours.
E. Common problems and solutions:
1) Cracks at internal and external corners:Real stoneDuring paint spraying, cracks sometimes appear at internal and external corners because an internal or external corner consists of two surfaces
At the junction, if real stone paint is sprayed, during the drying process two tensile forces in different directions will act simultaneously on the
Coating film, prone to cracking. On-site solution: for internal and external corners where cracks are found, use a spray gun to apply another thin over-spray, and after half an hour
then spray once more until the cracks are covered; for newly sprayed internal and external corners, take particular care during spraying not to apply too thick a coat at one time,
Adopt the thin-spray multi-layer method: respray after the surface dries, keep the spray gun at a greater distance, move it quickly, and do not spray vertically at corners and edges
Corner spraying can only use scattering, that is, spraying two surfaces so that the edges of the spray mist sweep into the internal and external corners.
2) Cracks on the flat surface: the main reason may be a large temperature difference in the weather, with a sudden drop in temperature, causing the inner and outer layers to dry at different speeds
differently, the surface dries while the interior does not, forming cracks; the on-site solution is to switch to a small-nozzle spray gun and apply multiple thin coats, controlling each
The drying speed of the layer; a slightly greater spraying distance is preferable.
3) Cracks appearing during film formation: during spraying, the coverage is not uniform enough or is too thick, and after a film forms on the coating surface,
cracks, or even cracks appearing after several weeks; this situation requires specific analysis. In addition to paying attention to the spraying method during construction
In addition, the formulation should be changed and trial production repeated when necessary.
4) Too much sand falling off during spraying: someReal stoneDuring paint spraying, more sand falls off; in severe cases it can reachabout 1/3, causing waste.
The main reasons: first, the construction method — during application, the air pressure of the spray gun was set too high and the spray gun was moved too fast. On the other hand,
Adding too much water to the coating makes it too thin; if it is too thin, the initial adhesion of the sand when applied to the wall is too low, and both will cause the sand to fall off. Spraying
at the time. Just adjust the air pressure to a suitable position, control the spray gun speed well during spraying, and try not to add
Dilute with water.
V. Paint surface flattening
1. Construction tool: smooth roller
2. Production process and requirements 1) Real stoneAfter the paint is sprayed, gently press with a smooth roller until the surface is flat
2) Dip a smooth roller in 200# gasoline or kerosene and lightly press it on the paint surface until it is flat
3. Precautions
1) When pressing the paint surface with the roller, apply even force to keep the paint surface flat and the texture balanced
2) Pay attention to the saturation of the surrounding coating after pressing some larger rock flakes, and there must be no gaps.
4. Common problems and solutions
VI. Removing the tape
1) Application tools: manual operation, utility knife
2) Production process and requirements
3) Precautions:
4) Common problems and solutions
(1) After spraying and flattening, the masking tape applied for the dividing lines should be peeled off at short intervals.
(2) Pending rockReal stoneAfter the paint is sprayed and flattened, use a putty knife to remove the [foreign matter] on the linesReal stonepaint, so that its edges and corners90 degrees as the standard,
Be careful not to damage the grooved treatment into an angular shape
VII. Sanding the wall surface
1) Construction tools: abrasive knife, abrasive paper
2) Production process and requirements
3) Precautions: use 400--600 grit sandpaper and gently smoothReal stone paintThe raised sand grains on the surface are sufficient. Be careful to apply force
It must not be too aggressive, otherwise it will damage the paint film and cause loosening at the base; in severe cases, it can lead to poor adhesion and cause the real stone paint to peel off.
Luo
4) Common problems and solutions
VIII. Topcoat Application Process
Method:1 Roller coating method, 2 Spray coating method,
1 Roller coating method
1) Construction tool — roller
2) Preparation before roller coating:
A. InspectionReal stonePaintWhether it is dry
B ClearReal stoneForeign matter on the paint
C. Prepare coatings and tools
3) Procedures and requirements,
A. Use a wool roller to evenly apply the water-based primer in two coats using a cross-rolling method.
B, Thickness: 30 microns 0.15KG/㎡
2. Spraying method,
1) Construction tools: primer spray gun, air compressor
2) Preparation before roller coating:
A. InspectionReal stoneWhether it is dry
B ClearReal stoneForeign matter on the paint
C. Prepare coatings and tools
3) Procedures and requirements,
A. Start the air compressor and adjust the pressure to 8KG,
B, Apply the water-basedClear topcoatLoad the paint into the spray gun and connect it to the air compressor.
C. Apply two uniform coats using a cross-hatch roller method.
D. Thickness: 30 microns, 0.15KG/㎡
3. Common problems and their treatment methods
1) Uneven coating: areas with uneven coating must be repaired,
2) ForReal stoneAreas with paint damage should be repaired beforeDryThen apply the topcoat.
4. Precautions:
1) During topcoat construction, the wall temperature shall not be lower than 10℃, the wall moisture content shall be less than 10%, and the air humidity shall be less than60%
2) When spraying the topcoat, it should beReal stonePerform after the paint is completely dry,
3) Application should be as uniform as possible; areas that do not meet technical requirements shall be repaired.
4) Construction is not possible below 5°C.