FLAT SiliconeLiquid granitePaint introduction:

Liquid graniteYesFLATA series brand of the company's environmentally friendly coatings, it meets today's environmentally friendly and energy-saving building exterior wall coating market. It enables architects, real estate developers and engineers to complete the design of building appearance, color and shape as well as the construction of energy-saving systems.Liquid graniteThe simulation fidelity can reach 100%, while providing rich creativity and functional advantages, thereby inspiring architectural designers' potential to create personalized and distinctive exterior wall textures and integrate color and personality into the function and form of exterior walls. This is a masterpiece that was previously unimaginable for exterior wall coatings.

FLATLiquid graniteThe coating is a unique environmentally friendly imitation marble material for building exterior walls, manufactured from imported organic silicone emulsion, special pigments, and various imported additives through a special process; after spraying, it ensures that all substrates are covered with a layer that produces a surface effect almost indistinguishable from granite slab.

Functions: easy to construct, strong texture, appearance closely resembling granite, good toughness, crack resistance, high strength, impact resistance, fading, no aging, flame retardant, heat resistant, good weather resistance, guaranteed for more than fifteen years; good texture, easy to shape, strong expressiveness, high hardness, no discoloration, dirt resistance, good cleanability, water resistance, crack resistance and seepage resistance.

I.Liquid graniteProduct application: widely suitable for interior and exterior walls, or coating on various cement, wood, glass, plastic and metal systems, and can also be used for renovation over existing coatings, stone or tile surfaces.

II.Liquid graniteTechnical parameters: Composition: high-performance water-based resin, imported pigments, imported additives.

III.Liquid graniteSupporting products: putty, water-based sealing primer, water-based gloss (matte) topcoat.

IV. Liquid granite product features:

1. Multiple colors can also be applied in a single spray. Even if improper application causes uneven pattern distribution, additional spraying can correct it without affecting the result. The appearance and patterns resemble granite or ceramic tile, and application is fast and simple.

2. It uses low-odor, non-toxic, low-VOC ingredients and is harmless to the environment during construction.

3. High solid content, which can form a relatively thick coating film, increase the waterproofing capability of exterior walls, and reduce the amount of topcoat used.

4. Made with imported pigments and super weather-resistant resin into a special coating for outdoor use, weather resistance.

5. Innovative special technical formula, resistant to washing, cracking, mold, and moss.

6. Low construction cost and a variety of customizable colors; spraying for buildings, villas, and artistic relief shapes is unmatched by ordinary traditional coatings.

7. The paint film has 3 times the elasticity of ordinary coatings and also has anti-fouling and self-cleaning functions.

V.Liquid graniteConstruction instructions: Standard equipment for liquid granite: pneumatic spray gun, pressure tank, pressure gauge.

VI. Liquid granite packaging and storage: packaging specifications: 5L, 18L; store in a cool, dry place, away from fire sources; sealed at room temperature, it can be stored for 6 months.

VII. Theoretical consumption of liquid granite: consumption: 0.3-0.7kg/㎡

VIII. Note: In addition to displaying samples, customers are welcome to come for color matching and custom production.

1. Construction preparation:

2.1 Construction base surface:

1.1. 1 Party A or the general contractor shall provide a substrate that meets the national Class II plastering surface requirements.

2.1.2 Provide technical disclosure to the client or general contractor, submit the construction process, and then negotiate the joint gap plan.

2.1.3 Check waterproofing, electrical circuits, traffic and material transport, storage, etc., and implement them.

2.1.4 Obtain the site management rules and regulations from the client or general contractor.

2.1.5 Based on the construction area and the condition of the construction surface, prepare the construction execution budget and the progress plan.

2.1.6 Establish the construction teams and formulate various management systems, such as quality inspection, progress,

2.2 Material preparation:

1.2. 1 Putty: adjust minor unevenness; special matching putty for exterior wall coating.

2.2.2 Primer: EM-PRIMER, used for sealing the base, promoting waterproofing and alkali resistance, and enhancing the adhesion between the base surface and the main material.

1.3. 3 Intermediate coat: the pure water-based multicolor main material breaks through the limitations of oil-based and water-based multicolor coatings; a single main material can contain a combination of more than 10 different colors; and it can be applied to create a granite texture, giving the multilayer coating film high strength, high wear resistance, and scrub resistance, while also having high elongation and crack resistance.

2.2.4 Topcoat: Highly self-cleaning, keeping the coated surface looking new, with anti-pollution and scrub-resistant properties; even if contaminated, it can be easily removed with a water-based cleaner; it is resistant to acid, alkali and saline-alkali conditions, and is not afraid of acid rain erosion.

2.2.5 Joint filler material: specially formulated joint paint with excellent waterproof performance.

2.3 Preparation of tools and supplies:

Dedicated electric mixer, mixing bucket, suspended platform or scaffolding, scraper, small sheet-metal scraper, platform scale, small trowel, putty knife, straightedge, air compressor, spray gun, etc.

2.4 Technical preparation:

1.4. 1 Substrate inspection and acceptance:

A. Use a two-meter straightedge and a wedge feeler gauge or dedicated inspection instruments to check the flatness and verticality of the substrate, the allowable deviation and the inspection method as shown in the figure:

No.

Project

Permissible deviation (mm)

Inspection method

1

Surface flatness

2

Inspect with a two-meter straightedge and a wedge feeler gauge

2

Internal and external corner verticality

2

Use a two-meter plumb board to check

3

Facade verticality

3

4

Internal and external corner squareness

2

Check with a square and a wedge feeler gauge.

5

Joint lines straight

3

Check with a five-meter line and a ruler

6

Flatness of the jointed surface

2

Three-meter straightedge, steel ruler

B. Visual inspection: the substrate should have no obvious cracks. If there are any, record them truthfully.

C. Inspection: no hollow areas. If any exist, record them truthfully.

D. Record the number and locations of window edges and lines that do not meet the requirements.

E. For external drainage pipes, wall-penetrating pipes for scaffolding, reserved air-conditioning holes, and loading openings, the quantity and locations, etc.: external drainage pipes should be installed and secured before coating application; reserved air-conditioning holes should, depending on the specific situation, either have distinct edges or be rounded and smooth; and the civil construction party should be urged to repair wall openings as early as possible. Plastering must be solid and slightly below the plane or flush with the large surface, ensuring the large surface is flat.

F. To ensure an overall effect with no color difference, exterior wall scaffolding should not have through-wall pipes or wall-adjacent pipes, and scaffolding requiring reinforcement should be replaced with through-window pipes and indoor reinforcement.

G. Test the moisture with a tester; the moisture should be below 10%. Test the pH with pH test paper; the pH value should be below 10.

H. After inspecting the base surface, carefully fill in the engineering contact form and submit it to the supervisor or the client. For areas that do not meet the requirements, cooperate and rectify them promptly.

2.4.2 Sample: .

Before large-area construction, some operators should prepare mock-ups according to the construction process requirements; after being signed and approved by the owner, supervisor, designer, and construction unit, these serve as the basis for acceptance upon completion.

2. Process procedure

A. FLAT (multicolor) coating construction procedure:

Base surface treatment

↓

Leveling putty application → joint reservation

↓

Application of repair and leveling putty

↓

Primer application

↓

Main coating application → Grid joint line painting

↓

Spray multicolor main material

↓

Topcoat clear finish

3. Method of operation

4.1 Substrate treatment

3.1. 1 Flatness inspection: carefully inspect the flatness of the wall surface with a 2M straightedge, and mark obvious protruding or recessed areas with a colored pen.

4.1.1 Spot repair: repair cavities or obvious depressions with cement mortar; for inconspicuous ones, spot repair with putty.

4.1.3 Sanding: Use a sander to grind the obviously protruding parts and repaired areas until they meet the requirement of ≤2mm.

4.1.4 Dust removal and cleaning: Use a brush, scraper, etc. to clean off adhered materials and floating dust on the wall surface.

4.1.5 Once the substrate repair is complete, with no floating dust and no other adhered materials, proceed to the next process.

4.2 Reserved joint grooves:

3.2. 1 Positioning and line snapping: position the dividing joints according to the drawings or the requirements of the client; for dividing joints with a width of 2.0CM, snap positioning lines with a width of 1.6CM using an ink line.

3.3. 2 Level the edges and corners of the joints.

4.3 Exterior wall putty application:

4.3.1 When mixing: use power tools to stir thoroughly and evenly.

4.3.2 Application method: troweling

After one full coat, level it with a scraper; after it dries slightly, generally 3–4 hours (on a sunny day), the next procedure can proceed.

4.4 Second putty application:

3.4. 1 When mixing, use power tools to stir thoroughly and evenly.

4.4.2 Application method: trowel coating/leveling.

Level with a trowel, wait briefly for it to dry, generally 3---4 hours (sunny weather), then sand carefully with sandpaper to remove trowel marks and joints.

4.4.3 Flatness ≤1.5MM, smooth surface, no trowel marks, no powdering. Dry for at least 24 hours before proceeding to the next construction process.

4.4.4 Take care to protect the reserved joint grooves; clean up any contamination immediately during putty troweling.

4.5 Primer roller coating or spraying:

3.5. 1 Application method: spray/roller.

A visible coating film forms on the putty layer surface, with no uneven color or blooming.

4.5.2 After application is complete, dry for at least 24 hours (sunny weather) before proceeding to the next process.

4.6 Spraying the intermediate coat:

3.6. 1 No filtration is required; place the main material in a container and spray. Operation is simple.

4.6.2 Application method: spray once, two passes.

4.6.3 Uniform coloring, no show-through or mottling; proceed to the next process.

4.7 Dividing joint line drawing:

4.7.1 Application method: brush coating.

Apply masking tape along both sides of the joint, then apply two coats of grid coloring coating. After it is slightly dry, peel off the masking tape.

4.7.2 Lines are straight, seam edges are neat, with no gaps, and seam surfaces are smooth.

4.8 Spraying the topcoat:

4.8.1 Application mixing ratio: main agent:water = 100:5

The paint after mixing and stirring requires no filtration and has no sediment.

4.8.2 Application method: spray coating, one application in two passes

One spray coating (thin coating), one pass (crosshatch). Allow to dry fully before further processing.

4.8.3 Evenly distributed, smooth to the touch, and uniform in overall color. After drying for 24 hours, proceed to the next process.

4. Points to note:

5.1 The construction temperature should be between 5-40°C. If the temperature is too low, the water serving as a chemical reaction medium cannot play an activating role, and the strength and hardness of the putty cannot be achieved; if the temperature is too high, surface moisture evaporates easily, and the system lacks the moisture required for reaction and is prone to powdering.

5.2 Construction should be carried out under conditions where the ambient relative humidity is less than 75%. Do not construct under the following conditions: rain, snow, fog, frost, strong wind, or relative humidity above 85%.

5.3 Ensure good ventilation, wear protective equipment, and avoid inhaling paint mist or getting it on the skin or eyes. If paint gets into the eyes, rinse immediately with clean water and seek medical attention promptly.

Topcoat application

B.Process steps

Process steps

Mix ratio

Number of coats (coats)

Consumption (kg/m2)

Interval (20°)h

Construction tools

Remarks

Base surface treatment

Before construction, first remove dirt from the substrate surface,Remove dust and other deposits; carry out construction after the substrate is dry

Elastic waterproof leveling putty (cement substrate)


2-3

2.0-3.5

12

Batch knife, putty knife, straightedge, etc.

The flatness of the substrate reaches1.5mm/2m

Elastic waterproof leveling putty (insulation substrate)

When constructing on an insulation substrate, a layer of alkali-resistant fiberglass mesh cloth should be laid over the entire substrate before applying the coarse putty

Elastic waterproof leveling putty


1-2

1.0-1.5

12

Batch knife, putty knife, straightedge, etc.

The flatness of the substrate reaches1.0mm/2m

Joint lines

Divide the wall into sections according to construction requirements, cut with dedicated tools, and fill with dedicated materials to achieve a smooth effect. During construction on insulated substrates, to ensure the integrity of the insulation layer, no cutting is performed; after the dividing joints are marked according to design requirements, paper tape is used for protective construction.

Sealing primer


1-2

0.1-0.15

2

Roller, wool brush, spray gun

Alkali-resistant sealing

high-elasticity intermediate coat/Modeling intermediate coat


1-2

0.2-2

18

Roller, wool brush, spray gun

Coloring

Joint tracing

Apply color to the dividing joints according to the designed joint color, and use masking tape for protection.

Colorful main materials


1

0.3-0.8

12

Dedicated spraying equipment

Do not dilute with water; has a strong multicolor effect

high-weather-resistance clear topcoat


1-2

0.1-0.2

12

Roller, wool brush, spray gun

Protection, aging resistance

Technical performance indicators:

Project

Indicator

Volatile organic compounds (voc)

≤100g/L


2h

Resistance to artificial weathering

Aging time

Appearance

Chalking

discoloration

2000h

No blistering, no peeling, no cracks

0grade

1grade

Water resistance

96hNo abnormalities

Alkali resistance

48hNo abnormalities

Scrub resistance

≥2000times

Stain resistance

5≤ after cycles2grade

Temperature change resistance

(-30-50c°)5no abnormality after cycles



Elongation

≥150%

Appendix:

multicolor paint-Comparison of the composite sandstone coating series with exterior wall stone performance

No.

Comparison items

Exterior-wall stone

multicolor paint-Composite sandstone coating

1

Construction period

The construction period is relatively long.

Short construction period

2

Durability performance

Excellent durability, can be guaranteed for use20years or more

The imitation granite series can be guaranteed for use15-20years or more

3

Safety performance

prone to falling off

No safety hazards

4

Adaptability to exterior wall surfaces

Irregular wall surfaces need cutting, which increases cost and waste

Can adapt to any irregular wall surface and decorate any curved, thin-edge and similar parts.

5

Development trends

Considering environmental protection and energy saving, it shows a downward trend

Due to its unique dust resistance, crack resistance, and rich color variation that is not easy to fade, it is increasingly welcomed by designers and developers, with a trend of increase.

6

Building load

Because the stone itself is heavy, it increases the load on the building.

only base putty, primer, mid-coat, topcoat and clear coat are required, with low load

7

Crack resistance

It has natural crack resistance, but the stone will crack under external force

The imitation granite series itself has high elasticity and high crack resistance, so as long as the building's main structure does not crack, the coating will not crack either

8

Waterproofing performance

A professional waterproof layer must be applied at the base of the building

Imitation granite is itself an excellent waterproofing material

9

Environmental performance

It has a certain level of radioactivity

Through comprehensive testing by the Quality Supervision and Testing Center, it is non-toxic and has no side effects during construction and use, and poses no harm to the environment or the human body

10

Economic performance

Dry-hung stone curtain walls are expensive to build and require very little labor.

The cost of the imitation granite series is only that of a dry-hung stone curtain wall30%Left and right

Party and information verification

Party:Guangdong Fulaite Building Materials Co., Ltd. · FLAT. / Company Introduction

When the text involves standards, inspections or material parameters, please verify against the original materials listed in the text and the corresponding product conditions. The original samples and reports can bePage of qualifications and inspection reportConsult; models, batches, and project conditions are different, and relevant data should be confirmed separately.

For engineering cooperation and import and export procurement, you can provide the location, required area and intended texture,Contact FLAT for samples and quotes。

FLAT · Guangdong Fulaite Building Materials Co., Ltd.

Make architecture more beautiful.

Focus on flexible stone (MCM soft stone/soft porcelain), providing texture selection, product information and order production coordination.

Copyright © 2012-2026 Guangdong Fulaite Building Materials Co., Ltd. All Rights Reserved Yue ICP No. 16084041

Headquarters Address:No. 2, West of Tong'an Avenue, Dongfeng Town, Zhongshan City, Guangdong Province
Public Security RecordGuangdong Public Network Security Preparation No. 44200002005257