Exterior wallCoatingsPre-construction requirements:
1. Substrate requirements: The base plastering has been completed and cured for about 20 days. The alkalinity (pH value) of the base is below 9, and the base has dried (for at least 15 days), with humidity below 8%. The base surface is flat, and the internal and external corners and corner lines are solid with clear outlines. The wall has no structural problems such as water seepage, cracks, hollowing, or blistering holes. There is no powdering or loose material, and no oil, grease, or other adhering substances.
2. The usedCoatingsThere is a factory certificate, and it has also been tested and meets the requirements of the relevant national standards and specifications.
3. The coatings used have been approved by the owner, and the sample wall has been approved by the owner, the supervisor and the design unit.
4. Exterior wallCoatingsBecause it is a water-based coating, it has relatively high requirements for construction and curing conditions. Construction and curing require a temperature above 5℃ and an ambient humidity below 85% to ensure proper film formation. Low temperatures will cause problems such as powdering and cracking of the coating film, while high ambient humidity will prevent the film from drying for a long time and lead to poor film formation. For exterior wall construction, weather factors should be considered: no rain for 12 hours before applying the coating to ensure the substrate is dry, and no rain for 24 hours after application to avoid the film being damaged by rainwater.
Exterior wall coating construction process:
Repair exterior wall—clean—fill putty, locally apply putty—sand smooth—apply fiberglass cloth—apply putty and sand smooth again—apply primer—apply first topcoat—apply second topcoat
1. Repair: Before application, defects on the substrate such as chipped edges and corners and holes shall be repaired with 1:3 cement mortar (or polymer cement mortar).
2. Cleaning: dust and powder can be removed with a broom, brush, or high-pressure water rinsing; grease ── clean with a neutral detergent; mortar ── remove with a shovel, scraper, etc.; mold ── rinse outdoors with high-pressure water, rinse with clean water and air-dry.
3. Filling putty and local putty scraping: if the wall is flat and smooth, putty may not be used; in addition to being easy to apply and sand, the putty should also have good strength and durability. During filling and local putty scraping, it is advisable to apply thinly rather than brush thickly. The putty should have better adhesion, lasting adhesion and water resistance.
4. Sanding flat: Sanding should be carried out after the substrate or putty is dry; do not sand wet, to avoid adhering to the sandpaper and affecting operation. The coarseness of the sandpaper should be determined according to the hardness of the surface being sanded; if the sandpaper is too coarse, sand marks will occur and affect the decorative effect of the coating. When sanding, first sand with coarse abrasive cloth or a sander, then sand with fine abrasive cloth, and pay attention to the flatness of the surface. After sanding, immediately remove surface dust to facilitate the construction of the next process.
5. Applying fiberglass mesh: use fiberglass mesh with uniform mesh density; do not use fiberglass mesh that is too dense for laying.
6. Scrape putty and then sand smooth: use polymer putty to scrape the surface flat. The main purpose is to level out the unevenness caused by applying fiberglass mesh and to prevent capillary cracks on the surface.
7. Paint application:CoatingsFor coating application, the moisture content of the substrate surface must not exceed 8%. In case of strong wind, rain, fog or other weather conditions, the topcoat must not be applied; during construction, a sample wall is required according to the design requirements, up until completion acceptance.
Exterior wall coating construction acceptance standards:
Exterior wallCoatingsConstruction must be free of missed coatings, show-through, powdering and peeling; there must also be no efflorescence or color bleeding, and the color must be consistent with uniform density; in addition, there must be no sagging, lumps or brush marks, and doors and windows must not be stained.
Exterior-wall decoration paintingCoatingsIt is a relatively common decoration method and also has relatively low decoration cost, so many people choose to use coatings to decorate exterior walls.
The exterior wall coating construction process and acceptance standards in this article are provided byFLATPaint (http://www.zsfulaite.com/) is compiled and published; if reproduced, please indicate the source.