First look at the conclusion
Material usage must first be clarified as dry material, wet material, net installation quantity, or purchase quantity. Substrate roughness, texture effect, number of coats, and loss all change actual consumption; the entire project cannot be estimated based on material name alone.
Usage calculation should retain measured evidence.
- Make a sample on a substrate consistent with the site, and record the effective area and actual consumption.
- The procurement quantity is calculated as the measured unit consumption multiplied by the net construction area, with loss and reserve quantities considered separately.
- Packaging specifications, residual amount in the opened pail, and consumption for different processes should be recorded separately and must not be mixed into the net consumption of the main material.
| Checklist item | Information or conditions to be confirmed |
|---|---|
| Unit of measurement | kg, L, square meters and their corresponding relationships |
| Measured conditions | Substrate, effect, number of coats and mock-up area |
| Procurement scope | Net usage, loss, material preparation, and packaging |
Scope of This Page and Materials
| Checklist item | Information or conditions to be confirmed |
|---|---|
| Discussion topics | Calculation method for real stone paint usage per square meter |
| Material category | Real stone paint |
| Nature of the material | Material selection notes; specific performance is subject to the corresponding product documentation and reports |
Original images and videos

Material source and scope of application
This article is a material selection and documentation verification note. The table lists items to be confirmed and does not indicate that the corresponding product has obtained a certain value or grade.